Is A Notice Of Intention To Recover Costs A Proper Notice Of Claim Under A Building Contract?

In Ledore Investments Ltd. v. Ellis-Don Construction Ltd., the Ontario Superior Court has recently held that a letter from a contractor to a subcontractor stating that “we intend to recover these costs from you” was a sufficient notice to the subcontractor to satisfy the notice provision of the building contract. Accordingly, the court set aside […]

Continue Reading

Can An Arbitration Award Survive Fraud?

When material evidence tendered to an arbitral tribunal is fraudulent, we expect the court having jurisdiction to be very inclined to set the award aside.  But as the recent decision of the English High Court in Chantiers de l’Atlantique S.A. v. Gaztransport & Technigaz S.A.S. demonstrates, “it ain’t necessarily so.”  In that case the award […]

Continue Reading